News

11.02.2014

The company Soyuztekhenergo (OPTEN Group of companies) has completed the installation of the MetrySense-4000 power lines insulation monitoring system for JSC Lenenergo...

Read more

26.11.2013

The company OPTEN has completed a project on 700 km power transmission lines survey for Réseau de Transport d'Électricité...

Read more

Version for printHomeThe first part of the project Hidroeléctrica de Cahora Bassa (Mozambique) is completed

The first part of the project Hidroeléctrica de Cahora Bassa (Mozambique) is completed

Working under Mozambican contract Opten has implemented Airborne laser survey on about 1800 km overhead power transmission lines. Our engineers have reviewed and summarized all laser reports and analyzed the statistics within four major areas: danger tree analysis - the customer received particular trees that potentially threaten the transmission lines; clearance violation analysis to ground and objects (being vegetation, tracks ets.), thermal rating and structure usage analysis.

 
Structure usage analysis has been performed with PLS-TOWER modeling, as the result of works there were detected particular towers with excess load on certain construction elements.


RUS
+7 (495) 644-4046